Project Details

Location: McLean, Virginia
Owner: Virginia DOT and Transurban (P3)
Contractor: Lane Construction Corporation

The I-495 Express Lanes Northern Extension, known as 495 NEXT, is bringing new capacity and connections to one of Northern Virginia’s busiest transportation corridors. The 2.5-mile extension runs from the Dulles Corridor to the George Washington Memorial Parkway near the American Legion Bridge, adding two express lanes in each direction along I-495.

The $660 million project was delivered through a public-private partnership between the Virginia Department of Transportation (VDOT) and Transurban, with Lane Construction Corporation serving as the design-builder. Construction began in March 2022, and the new express lanes opened in November 2025, ahead of schedule. Full project completion followed in mid-2026.

As part of the project, Geoquest USA supplied approximately 88,000 square feet of Reinforced Earth® MSE walls, along with approximately 7,000 linear feet of half connector and coping. The project also included approximately 7,000 square feet of temporary walls to support construction activities within the constrained interstate corridor.

Several structures involved unique design considerations, including:

  • MSE walls supporting soundwalls founded on drilled shafts
  • MSE walls with soundwalls mounted on barriers
  • Standard barrier and moment slab designs
  • Moment slabs supporting barriers with attached soundwalls.

Additional challenges included incorporating drainage inlets into barriers, designing acute wall corners, evaluating crane loading adjacent to MSE walls, coordinating wall phasing requirements, and accounting for abutment pile loads applied adjacent to MSE wall panels.

To help the job site stay on schedule, our project team was very hands-on with the contractor. Throughout the project, Geoquest was reviewed the installation schedule monthly with both contractors, updated casting and delivery schedule accordingly, and coordinated between the precaster and installers on site.

Beyond the express lanes, 495 NEXT included replacement or rehabilitation of seven bridges, a new shared-use path for bicyclists and pedestrians, upgraded and new noise walls, stormwater improvements, and other environmental and multimodal improvements.

The project has also received significant industry recognition. In 2026, 495 NEXT was named Project of the Year – Community Impact at the American Road & Transportation Builders Association’s Public-Private Partnerships in Transportation Conference. It was also recognized in the 2026 America’s Transportation Awards competition for its benefits to the surrounding community.

For Geoquest, 495 NEXT adds another major Northern Virginia transportation project to our portfolio, showcasing the use of Reinforced Earth® retaining walls within a complex, highly constrained interstate expansion.